The Spire, St Anthony’s – Hospital Extension

ABEC has been appointed by ESG plc to complete the building management system for the new theatre block, within a 39 week programme.

The BMS works consisted of 2no control panels located in the boiler plant room and roof plant room, serving 5no AHU’s, 2no chillers, 12no Boilers and associated sequencer, 3no sets of pumps and various monitoring of equipment and included a new BMS front end, and also networking to the existing BMS system on site in the adjacent building.

Services Included
InstallationMaintenance
Key Facts

Date:
January 2016

The project consisted of a new operating theatre block consisting of 6no operating theatres, and the various plant required to serve these new theatres.

The hospital needed to remain operational at all times.